Minnesota Power Hydro Dam: The New Era of Renewable Energy

Posted by Kimberly Walters on February 12, 2024

We're at Minnesota Power's hydroelectric dam in Scanlon, Minnesota, to replace 7 of the structure's Tainter gates. Extending the life of this renewable energy source by 50 to 100 years, the Scanlon Dam Gate Replacement Project enables the further creation of clean, renewable power provided to local communities. 

We were pulled into the project very early on during the design phase of the project. Both Nelosca and Minnesota Power attribute the project's success to early contractor involvement.

Read More

Dam Rehabilitation and Operational Updates to 100-Year-Old Structure

Posted by Kimberly Walters on August 09, 2023

Sandy Lake Dam is owned by the United States Army Corps of Engineers (USACE), St. Paul District. The USACE identified that the original concrete structure needed repairs and improvements to address immediate safety concerns. Because the dam structure was more than 100 years old, the USACE used this as an opportunity to have Nelosca rehabilitate the dam and update many of its operational features.

Our new video shows you how we did it! 

Read More

Executing Major Rehab on an Existing Lock in 105 Days

Posted by Brady Wateland, Project Manager on March 18, 2021

80 years old and 35 years since its last rehab, LaGrange Lock and Dam in Versailles, IL was in major need of rehabilitation. Nelosca partnered with prime contractor Shimmick Construction (Shimmick) and the U.S. Army Corps of Engineers (USACE) Rock Island District, along with hundreds of crew members, to execute quality repairs through the existing lock.

Read More

Nelosca Proudly Establishes Joint Venture with Ahtna

Posted by Kimberly Walters on February 15, 2021

Nelosca Technologies (Nelosca) formally announces their Small Business Administration (SBA) 8(a) certified joint venture with Ahtna Marine & Construction Company, LLC (AMCC). Publicly titled the Ahtna – J.F. Nelosca JV, the partnership establishes a mentor protégé relationship between Nelosca and Alaska Native Corporation subsidiary AMCC.

Read More

Tainter Gate Operation: Monitoring Tension for Longevity

Posted by Jeff Steiber on November 27, 2018

At Nelosca, we work on dams of various sizes and functions. Very few new dams are built each year, so most of our work consists of rehabilitation and repairs. Dams are built to last for long periods of time, however certain components require periodic repairs and replacements. Radial gates, often referred to as Tainter gates, consist of components most commonly in need of attention. In our experience, we have found certain best practices that will increase the longevity of these gates, as well as increase their functionality.

Read More